This document separates supported deployment modes. They use the same static PWA artifact but do not offer the same HTTP-header or operational guarantees.

PWA Modes

nsite reference workflow

.github/workflows/deploy.yml runs the release gate, builds the PWA and publishes it with nsyte using a NIP-46 bunker capability. It runs only when dispatched by hand from the GitHub Actions tab: release tags are not pushed to the public mirror, so nothing publishes the nsite automatically when a release is tagged. This is a reference Nostr-native delivery path. It uses an SPA fallback and hash routing.

nsite gateways control their response headers. They cannot be assumed to provide the same CSP, anti-framing, cache-control, or other HTTP-header policy as a conventional host. Treat nsite as a delivery option, not as equivalent to a configured web origin.

Conventional static host

Serve packages/app/build/ from a configured static host such as nginx, Cloudflare Pages, or Netlify. This is the appropriate mode when the operator needs explicit response headers.

Three nginx specifics, each of which bit the reference deployment:

Coordinator

Log rotation

packages/coordinator/nostrautica-coordinator.logrotate is the reference logrotate fragment; install it as /etc/logrotate.d/nostrautica-coordinator.

It uses copytruncate, and that is not optional: the systemd unit writes with StandardOutput=append:, which holds the file open for the life of the process and never reopens it, so a rename-based rotation would leave the daemon writing to an unlinked inode and the live log would silently stop growing. The daemon's stdout descriptor carries O_APPEND, so after truncation its next write goes to offset 0 rather than leaving a large sparse hole.

Without this the log simply grows forever, the reference deployment reached ~37 MB over seven weeks before anyone looked, on a filesystem shared with other services. Note that restart-coordinator.sh greps this exact path for the daemon's readiness marker, so the path must stay stable, and a rotation landing inside a deploy's readiness window can make that grep miss.

Startup time

restart-coordinator.sh waits for the daemon's own readiness line ([coordinator] running — watching for installs, submissions, admin commands, matched as the whole line so attendee text in the log cannot fake it) and reports how long it took. Two thresholds, doing different jobs:

default override on breach
soft 60 s COORDINATOR_READY_WARN prints a warning, deploy still succeeds
hard 240 s COORDINATOR_READY_TIMEOUT fails the deploy step

The hard limit is deliberately far above anything normal. It does not bound a crash (the readiness loop fails within a second when the unit goes inactive, whatever the limit is). It bounds a daemon that is alive and never becomes ready. A limit set too short is the worse failure: the script does not kill anything, so the daemon starts normally while the deploy prints "coordinator is NOT running" and sends whoever pushed into an incident that is not happening.

The soft threshold is the part worth watching. The limit was 45 s until a 2026-09-04 deploy came in at 44 s, which is not a margin.

What actually drives it is per-event startup work, not inbox backfill. That correction is worth stating plainly, because this section previously blamed the coordinator's own inbox backfill growing with the daemon's wrap history (98 wraps on one boot, 153 two months later) and told you to go read the [boot] … backfill counts. A 2026-09-10 restart measured 52 s with the wrap count down to 45 — startup rose while the thing it was blamed on fell, so that story cannot be the explanation.

You no longer have to reconstruct this from timestamps. The daemon now times its own boot and prints the breakdown immediately before the readiness line — so it is inside the window the deploy measures and cannot flatter it:

[boot] ready in 1.2s — 4 event(s); phases:
[boot]   install:config-fetch 1.2s ×4
[boot]   install:chat 1.2s ×4
[boot]   chat:roster-scan 1.2s ×4
[boot]   install:inbox-backfill 1.2s ×4
[boot]   boot:restore-events 0.9s
[boot]   boot:coordinator-inbox 0.3s

Phases nest (install:chat contains chat:roster-scan), so an enclosing phase legitimately exceeds the sum of the lines under it, and ×N is the number of events that phase ran for. When the soft warning fires, read these lines.

What the 9–12 s per event was

Measured against a restart with four chat-enabled events of twelve members each, over a transport charging 300 ms per relay read. (The measurement harness was a throwaway; what ships is a regression test asserting the structure — one read per roster, several events in flight at once — because a wall-clock assertion in CI is a flake generator.)

before after
ready in 17.2 s 1.2 s
relay reads 57 13
chat:roster-scan 14.5 s (84% of the boot) 1.2 s

and at eight events of twenty-five members: 67.9 s → 2.2 s, 225 relay reads → 25. Two things were wrong. The first accounts for most of it (17.2 s → 4.0 s on its own); the second took the remainder (4.0 s → 1.2 s):

Everything genuinely shared was already serialized a layer down and still is: node:sqlite is synchronous, MarmotClientMls chains MLS commits per group, and the roster walk takes the per-member subject lock. The per-member work within one event stays serial on purpose — what is left after the batched read is a local membership check and, for a member needing repair, an MLS Add, and Adds against one group serialize anyway (the concurrent-commit hazard), so concurrency there would buy queueing rather than speed.

The other two costs from the 2026-09-10 measurement are untouched, and are now a much larger share of a much smaller total: the coordinator-inbox backfill (~5 s at 45 wraps) and the kind 31611 announce publish (up to ~4.4 s). The announce remains the cheap lever if one is ever needed: main.ts awaits it between coordinator.start() and the readiness line, and NostrClient.publish resolves on the first relay ack — but when no relay acks (all five timed out on that boot) it pays nostr-tools' full publish timeout before the daemon reports ready. Nothing waits on that announcement.

To read a real boot:

ssh <coordinator-host> 'grep -a "\[boot\]" ~/log/nostrautica-coordinator.log | tail -20'

If the slowest line is a per-event phase and there are simply more events than there used to be, the next lever is RESTORE_CONCURRENCY — not deferring work past the readiness line, which only makes the metric lie.

Reading the log

Every line the daemon writes through its log helpers starts with [MM-DD HH:MM:SS], UTC month-day and time. Builds before the 28-Oct audit fixes printed the time alone ([HH:MM:SS]). Lines printed bare by main.ts, including the readiness line above, have no prefix. To read one day: grep -a '^\[10-29 ' <log>.

Lines worth knowing, because each one is printed once per episode, not once per occurrence:

Line Meaning
[relay] <url> is refusing REQs ("…") — backing off for 5 min … The relay answered "too many concurrent REQs" (or similar). It is degraded for 5 minutes: at most 2 fetches at a time, and any subscription it refused is re-sent after 30 s, then 60 s, 120 s, 300 s. Printed again at most once per 5 minutes, with the count of refusals in between.
[relay] <url>: more than 8 long-lived REQs needed … Long-lived subscriptions are multiplexed (up to 20 filters per REQ, 8 REQs per relay). Past that the daemon opens another REQ rather than drop a subscription. Said once per relay.
[chat] watching 30443 for N eligible chat identities across M chat event(s) … The single daemon-wide key-package watcher, re-opened when the eligible set changes (approval, attestation, revoke).
[chat] <handler> failed for <event>: … (N similar failure(s) suppressed …) A chat watcher, 445 ingest, link sweep or roster republish threw. At most once per handler and event per 5 minutes.
[chat] boot: re-queued poisoned chat_sync_member #N for … — fresh retry budget Every boot gives poisoned chat syncs one more full retry tail. An organizer reprocess does the same for its event.
[jobs] queue: … The queue heartbeat. Printed when the queue changes, and repeated at most every 10 minutes while it does not.
[coordinator] announce (kind 31611) failed: … retrying in the background … / [roster] address upgrade (R-53) failed: … Background retries back off and log the first failure of a streak, then the success or the give-up, with the count.

Runtime

The Dockerfile and systemd unit are reference deployment material, not a complete production runbook. The coordinator needs Node 22.13+ (node:sqlite is behind a flag before 22.13), ffmpeg/ffprobe, protected provider credentials, a stable coordinator identity, relay connectivity, and durable writable SQLite storage.

The SQLite volume is not disposable when Marmot chat or Cashu is enabled. See COORDINATOR-OPERATOR-GUIDE.md for backup, restore, lifecycle, and operational limitations.

Reference Production Instance

The public reference instance is an operator-managed conventional static host plus coordinator deployment. Its host-specific commands, identities, and secrets are intentionally private and are not a portable deployment recipe. Do not assume that its deployment mechanics or HTTP headers apply to an nsite deployment.

Release Verification

Nothing runs these steps for you on the production path. The GitHub Actions release gate (.github/workflows/release-gate.yml) runs on the public mirror, for pull requests, mirror syncs and the manual nsite deploy. The reference production instance deploys by a push to a separate private remote, and a red gate does not stop that push. Until the deploy itself runs the gate, these steps are a checklist the person pushing has to follow.

  1. Run pnpm check.

  2. Build the PWA and run a clean-context coordinator Docker build: it must succeed from a checkout with no working-tree state:

    rel="$(git describe --tags --always --dirty)"; sha="$(git rev-parse HEAD)"; ts="$(git show -s --format=%cI HEAD)"
    cc="$(mktemp -d)"   # a FRESH directory: tar -x overlays onto whatever is there
    git archive HEAD | tar -x -C "$cc"
    docker build -f docker/coordinator.Dockerfile \
      --build-arg RELEASE_ID="$rel" --build-arg GIT_SHA="$sha" --build-arg BUILD_TIMESTAMP="$ts" \
      "$cc"
    rm -rf "$cc"
    

    Never extract into a directory a previous run used. pnpm-workspace.yaml globs packages/vendor/* from disk, so a package retired since that run would survive in it, change the workspace graph, and fail --frozen-lockfile (or worse, pass against code that is no longer in the repo).

    The image's dependency layer copies the lockfile, patches/, and the vendored Marmot/MLS workspace packages before pnpm install --frozen-lockfile, and pins the base image by digest, so this build is reproducible from a clean checkout. Keep it in the release gate. A git archive checkout has no .git, so the coordinator's own git-describe provenance is unavailable inside the container: pass the RELEASE_ID/GIT_SHA/BUILD_TIMESTAMP build args (as above) so the running daemon reports the real release instead of v<pkg> / gitSha: unknown. OCI image labels (org.opencontainers.image.*) are set from the same args.

  3. Verify app and landing HTTP status, CSP/header policy for the chosen host, and service-worker update behavior. Confirm the build you meant is the one being served: the shell's precache revision in sw.js ends in the commit's 12-character SHA (see VERSIONING.md):

    curl -s https://<host>/app/sw.js | grep -oE 'index.html",revision:"[^"]*"'
    git rev-parse --short=12 HEAD
    

    A deploy that printed success but whose build step failed serves the previous sw.js, so this check catches it and an HTTP 200 does not.

  4. Exercise an event flow appropriate to the release: join, approval, media where applicable, and coordinator health.

  5. Record the Git revision and deployed app/coordinator versions.

Rollback

Every deployment mechanism in this document is one-directional: it describes how to ship a newer build and says nothing about getting back to an older one. That is the wrong shape for an incident, where the decision is usually "put back what worked" and the time to discover the procedure is not while the site is down.

Decide first whether the coordinator database has migrated. This is the only step that is not reversible by re-deploying code. The store refuses to open a database whose user_version exceeds what the binary knows, so rolling the coordinator back past a schema bump means restoring a database file, not just an older build:

# On the coordinator host — what schema does the live DB carry?
sqlite3 -readonly "$HOME/nostrautica/packages/coordinator/coordinator.sqlite" "PRAGMA user_version;"
# What does the build you want to roll back TO know?
git show <target-ref>:packages/coordinator/src/store/db.ts | grep 'SCHEMA_VERSION ='

If the live number is higher, you need a pre-migration backup. No backup, no rollback, go forward with a fix instead. Look in these places, in this order:

What Where Written by
Automatic pre-migration backup beside the database: $HOME/nostrautica/packages/coordinator/coordinator.sqlite.v<N>-<timestamp>.bak the daemon itself, whenever it finds a pending migration (VACUUM INTO)
backup CLI snapshot wherever its destination argument pointed (the operator guide's examples use /home/nostrautica/backups/) an operator or a timer, see COORDINATOR-OPERATOR-GUIDE.md §5
Hand-taken copy wherever the operator put it ($HOME/ in the reference deployment's checklist) an operator, with sqlite3 … ".backup '…'"

Every name states the schema version the file CONTAINS (v<N>), not the one it precedes: restore the one whose v<N> the build you are rolling back to knows.

Static site (landing / /app / /docs). The build is a pure function of the commit, so rolling back is re-deploying the older commit; nothing on the serving host holds state.

git push origin <good-sha>:main --force-with-lease

--force-with-lease, not --force: it refuses if someone else has pushed since you last fetched, which during an incident is exactly the case you cannot afford to guess about. Then verify the served bundle is the one you meant, using the sw.js revision check in the release-verification section above: the OK markers only prove a build ran.

Coordinator. The same push redeploys and restarts it. Two things to check afterwards, in this order:

ssh <coordinator-host> 'systemctl --user is-active nostrautica-coordinator;
  systemctl --user show nostrautica-coordinator -p NRestarts --value'

NRestarts climbing means the daemon is dying and being respawned, with Restart=always that looks identical to "up" from the outside, and a rollback onto a database it cannot open is one of the ways to get there.

Restoring a database. Stop the daemon first: a copy taken or placed while it holds the WAL is not a consistent database.

ssh <coordinator-host> 'set -e
  systemctl --user stop nostrautica-coordinator
  DB="$HOME/nostrautica/packages/coordinator/coordinator.sqlite"
  mv "$DB" "$DB.failed-$(date +%Y%m%d-%H%M%S)"   # keep it — it is the only copy of what went wrong
  rm -f "$DB-wal" "$DB-shm"                       # stale WAL/shm belong to the file you just moved
  cp "$HOME/nostrautica/packages/coordinator/coordinator.sqlite.vN-<timestamp>.bak" "$DB"   # or the backup you chose above
  systemctl --user start nostrautica-coordinator'

Keep the failed database rather than deleting it. It is the only record of the state the incident happened in, and a migration that corrupted data is diagnosed from it, not from the backup that replaced it.

What a rollback does not undo. Anything already published to relays (a roster, a directory entry, a match list, a coordinator status) is out and stays out; replaceable events can be superseded but not withdrawn, and gift wraps cannot be recalled at all. Provider spend is likewise spent. So a rollback restores the code and the local state, not the world's view of what happened, which is worth saying to an organizer before they ask.